Romana English
Precast elements made of reinforced pre-stressed concrete

Roof precast elements

Precast elements for skew back covers

Name Length
[cm]
Width
[cm]
H
[cm]
h
[cm]
Weight
[kg]
Volume
[mc]
Reinforcing Accepted loadings on one concrete arch rib
[kg/ml]
P1 * P2 ** P3 ***
IPCT Project type no.91 - specification 2, 3
Fire resistance limit: 90 minutes
ECP
1,5X9
a 890 149 44 40 2750 1,1 2X2TBP12 285 390 580
b 890 149 44 40 2750 1,1 2X3TBP9 225 335 470
c 890 149 44 40 2750 1,1 2X2TBP9 135 190 285
d 890 149 44 40 2750 1,1 2X1TBP9 110 155 240
ECP
1,5X12
a 1190 149 55 50 3970 1,59 2X5TBP9 240 375 495
b 1190 149 55 50 3970 1,59 2X4TBP9 185 255 395
c 1190 149 55 50 3970 1,59 2X2TBP12 160 215 350
d 1190 149 55 50 3970 1,59 2X3TBP9 125 170 250
ECP
1,5X15
a 1465 149 69 65 5550 2,22 2X3TBP12 225 360 490
b 1465 149 69 65 5550 2,22 2X5TBP9 200 305 430
c 1465 149 69 65 5550 2,22 2X4TBP9 145 200 330
d 1465 149 69 65 5550 2,22 2X2TBP9 120 165 280
ECP
1,5X18
a 1765 149 80 75 7200 2,88 2X4TBP12 205 355 480
b 1765 149 80 75 7200 2,88 2X3TBP12 130 185 325
c 1765 149 80 75 7200 2,88 2X4TBP9 66 115 195


*P1 - the accepted loading uniformly distributed corresponding to the normal exploitation limits under a long – term loading stress
**P2 - the admissible loading per element as full load corresponding to the limits of normal exploitation under a long – term load
***P3 - accepted loading corresponding to the last limit of resistance

Precast elements for straight back covers and caisson section

Name Length
[cm]
Width
[cm]
H
[cm]
Weight
[kg]
Volume
[mc]
Reinforcing Accepted loadings on one concrete arch rib [kg/ml]
P1 * P2 ** P3 ***
IPCT Project type no.91 - specification 1
Fire resistance Limit: 90 minutes
EP
1,5X6
a 593 149 24 1500 0,6 2X1TBP12 240 275 320
b 593 149 24 1500 0,6 2X1TBP12; 2X10PC60 210 280 440
c 593 149 24 1500 0,6 2X1TBP12; 2X12PC60 205 285 500


*P1 - the accepted loading corresponding to the 0,03mm crack middle opening at pre-stressed reinforcement level under the stress given by the full load
**P2 - the accepted loading corresponding to the 0,01mm crack middle opening at pre-stressed reinforcement level under the stress given by loading
***P3 - accepted loading corresponding to the last limit of resistance

Cross beams

Name Length
[cm]
Width
[cm]
H
[cm]
h
[cm]
Weight
[kg]
Volume
[mc]
Reinforcing
Project type 2115/v -5104/lia- 5029 (loading according to IPCT)
Fire resistance Limit: 90 minutes
G12-6 9T 1180 32 95 45 3326 1,33 9 TBP 12
G15-4A 1480 50 138 86 8200 3,28 16 TBP 12
G18-4A 1780 50 145 86 10360 4,143 20 TBP 15
G21-1 A1 2080 60 147,5 90 15050 6,02 30 TBP 12
G24-A2 2380 60 150 90 17450 6,98 30 TBP 12

Longitudinal beams

Name Length
[cm]
H
[cm]
h
[cm]
Weight
[kg]
Volume
[mc]
Reinforcing Accepted loadings on
one concrete arch rib
[t/ml]
P1 cap* P2 cap** P3 cap***
IPCT Project type no.91- specification 6
Fire resistance Limit : 90 minutes
G6-T a 595 55 45 2250 0,9 12 TBP 12 3,87 5,1 7
b 595 55 45 2250 0,9 10 TBP 12 3,63 4,8 6,7
c 595 55 45 2250 0,9 8 TBP 12 3,19 4,3 6
d 595 55 45 2250 0,9 6 TBP 12 2,56 3,56 5
e 595 55 45 2250 0,9 4 TBP 12 1,76 2,55 3,7
GΨ6-15 a 595 47(18) 37(18) 3420 1,368 14 TBP 12 5,33 6,9 9,9
b 595 47(18) 37(18) 3420 1,368 12 TBP 12 4,54 6,35 9,15
c 595 47(18) 37(18) 3420 1,368 10 TBP 12 4 5,8 8,4
d 595 47(18) 37(18) 3420 1,368 8 TBP 12 3,26 5 7,2
e 595 47(18) 37(18) 3420 1,368 6 TBP 12 2,28 4 5,8
GΨ6-18 a 595 47(23) 37(23) 3630 1,425 16 TBP 12 6,52 8 11,9
b 595 47(23) 37(23) 3630 1,425 14 TBP 12 5,58 7,4 10,95
c 595 47(23) 37(23) 3630 1,425 12 TBP 12 5,04 7 10,3
d 595 47(23) 37(23) 3630 1,425 10 TBP 12 4,05 6 9
e 595 47(23) 37(23) 3630 1,425 8 TBP 12 3,41 5,3 7,8
f 595 47(23) 37(23) 3630 1,425 6 TBP 12 2,76 4,35 6,45


*P1 - the accepted loading uniformly distributed corresponding to the normal exploitation limits under a long – term loading stress
**P2 - the admissible/permissible loading per element as full load corresponding to the limits of normal exploitation under a long – term loading
***P3 - accepted loading corresponding to the last limit of resistance

Handling:

The handling of the products is done by hanging, inside the mounting holes or inside the terminal lug. It’s also done mechanically using a lifting device corresponding to the maximum load demand and to the span.

Transportation:

It is done by train or by cars endowed accordingly. The precast element shall protected against sliding and overturning and shall be fixed to the means of transport.

Storing:

It is done in adequate places, on brackets, avoiding the contamination with substances that may destroy the concrete during usage. The brackets shall be placed at adequate distances according to the length of the product.